KeymasterHalfway into the current financial year Eskom has completed only eight of the 54 outages in its reliability maintenance programme for the period. That is not even 15%.
This, the utility says, is âdue to break downs and changes in outagesâ. The plan is constantly being revised and outages that have flexibility are rescheduled accordingly, it adds.
Read:
These four charts show the Eskom crisis is just beginning
Beware governmentâs spin on âfixedâ Eskom
ANC signals caution on green energy transition
It further disclosed that 19 outages have been deferred, four of them beyond the end of the period on 31 March 2024, and three have been cancelled.
A total of 15 additional outages have been completed.
In the previous financial year 79 outages were scheduled, 45 of which were completed, while 17 in progress at year-end.
This information provided by Eskom comes shortly after its system operator in its latest weekly system status bulletin increased the base assumption of unplanned breakdowns to 16Â 000MW, rather than the previous 15Â 000MW.
Kusile question mark
In its 52-week outlook, which forms part of the bulletin, the system operator also no longer provides for a step-change expected when the three units at Kusile Power Station that are out of action following a flue duct collapse late last year, are expected to return to service at the end of 2023.
This despite assurances by Electricity Minister Kgosientsho Ramokgopa that the units will return to service in November, adding 2Â 400MW of generation capacity. This equals more than two stages of load shedding.
Read:
How Eskom managed to tame load shedding
Fewer power cuts are âno accidentâ â Ramokgopa
Power cuts may end sooner than expected
The system operator is now forecasting constant Stage 3 or higher load shedding in two of the three scenarios it provides weekly.
Eskom outlook
This is the forecast demand versus available generating capacity for each week for 52 weeks ahead.
Colour coding â ranging from Green (no shortage) to Red (worst case) â is used to indicate the absence or presence of a capacity constraint.
Source: Eskom
Eskom outlook published in week 35, 2023
Source: Eskom
Eskom outlook published in week 36, 2023
Source: Eskom
Concern about the state of Eskomâs generation fleet deepened recently when Stage 6 load shedding returned for about 10 days, although the utility has been able to return several units to service and decreased the intensity of load shedding in the past few days.
âMore variable than windâ
In addition, Isabel Fick, head of the system operatorâs office at Eskom, said at an Energy Systems Research Group event at the University of Cape Town that the performance of Eskomâs coal fleet is now more variable than that of wind and solar power.
According to Fick the variability of the 40Â 000MW coal fleet is about 4Â 000MW, compared to 150MW for the more than 6Â 000MW of renewables connected to the grid.
Eskom has been battling to reduce the extent of generation capacity offline due to unplanned breakdowns to less than 15Â 000MW, although it reported on Tuesday 19 September a reduction to 13Â 577MW.
Professor Anton Eberhard, professor emeritus and a senior scholar at the Power Futures Lab at the University of Cape Townâs Graduate School of Business, used a graph compiled by energy analyst Clyde Mallinson to illustrate on X the reality of Eskomâs breakdowns and points to the unrealistic expectations of politicians:
Total energy availability has also been stubbornly below 60%, despite Ramokgopa saying at times it has improved to 60%.
Cabinet, in its latest statement published on 14 September, blamed the implementation of Stage 6 load shedding on the âconcerted implementation of the planned fleet maintenance programmeâ and said it was âa regress from the trends that prevailed in the previous weeks of lower stages of load sheddingâ.
It continued: âCabinet was assured that the current implementation of increased stages of load shedding is a short-term phase as Eskom prepares for more sustained and lessened stages of load shedding in the not-so-distant future.â
ANC secretary general Fikile Mbalula, in a post on X, once again set the goal of ending load shedding by the end of this year.
In the meantime, former Eskom executive Matshela Koko said on X Eskom is biting off more than it can chew with its ambitious maintenance targets.
He says the amount of maintenance that Eskom can successfully execute is linked to the number of available skilled staff, equipment and spares.
âYou can only do so much. When you do more, your results deteriorate,â says Koko, under whose command load shedding was temporarily halted.
âThere is nothing to show for all the philosophy maintenance since 2018,â he says.
He warns that routine maintenance that must be done daily may be neglected in the face of an aggressive reliability maintenance programme, which may explain the high level of breakages at Eskomâs coal-fired power stations.